Project Description
Name/Location: Rock Springs, WY
Year: Completed in October 1996
Work done: 8” HP replacement – install approx. 40,000 ft of 8” removal & replacement of critical feeder pipeline for city of Rock Springs. The pipeline was routed through one of the busiest sections of town. We pre-located over 100 pipelines and cable crossings with a vacuum type, or soft location system. The project also required five separate test sections that each had to be hydro-tested, de-watered, dried and place into service before proceeding into the next section. The project was completed in October 1996 in time to provide fuel for the critical winter heating season.