Project Description
Name/Location: Spanish Fork, UT – 1100 & 1500 East from 1500 South to 1st East
Year: Project started 6/5/03 and was completed on time 8/1/03.
Work done: Work consisted of excavating and removing old 18” steel pipeline, re-excavating, weld, wrap & install new 24” HP line under streets, intersections, event grounds, parks, and state highways. Pipeline was backfilled, compacted, restoration of asphalt, curb and gutter, sidewalk, fences , lawn, and trees replaced. Due to existing utilities pipeline was installed at a depth of 7’ to 8’.